• About Us
  • Privacy Policy
  • Terms of Use
  • Breaking News
  • Explainers
  • Listen Live
Wednesday, June 24, 2026
Citinewsroom - Comprehensive News in Ghana
Advertisement
  • Home
  • News
    • Regional News
      • Ahafo Region
      • Ashanti Region
      • Bono East Region
      • Bono Region
      • Central Region
      • Eastern Region
      • Greater Accra Region
      • Northern Region
      • North East Region
      • Oti Region
      • Savanna Region
      • Upper East Region
      • Upper West Region
      • Volta Region
      • Western Region
      • Western North Region
  • Sports
    • World Cup
  • Politics
  • Business
  • Entertainment
  • Articles
  • Explainers
  • Editorials
No Result
View All Result
Citinewsroom - Comprehensive News in Ghana
  • Home
  • News
    • Regional News
      • Ahafo Region
      • Ashanti Region
      • Bono East Region
      • Bono Region
      • Central Region
      • Eastern Region
      • Greater Accra Region
      • Northern Region
      • North East Region
      • Oti Region
      • Savanna Region
      • Upper East Region
      • Upper West Region
      • Volta Region
      • Western Region
      • Western North Region
  • Sports
    • World Cup
  • Politics
  • Business
  • Entertainment
  • Articles
  • Explainers
  • Editorials
No Result
View All Result
Citinewsroom - Comprehensive News in Ghana
No Result
View All Result

Abandoned, delayed projects by MMDAs cost Ghana GHS35.4M – Audit report

Delali Adogla-BessabyDelali Adogla-Bessa
August 12, 2021
Reading Time: 2 mins read
abandoned project

File photo

ShareShareShareShare

Abandoned and delayed projects cost Ghana GHS35.4 million in 2020 according to an audit report released by the Auditor-General on the use of the District Assemblies Common Fund (DACF).

The figure forms part of contract irregularities committed by various Metropolitan, Municipal and District Assemblies (MMDAs) totalling GHS45.69 million.

Despite these gaps, the Auditor-General’s department noted that MMDAs still awarded fresh projects when earlier ones had not been completed.

This led to a suspension of work because of non-payment of work certificates.

For example, the North Gonja District Assembly spent GHS370,270.24 on four projects awarded in 2016 but have been abandoned at various stages of completion.

The Sefwi Akontombra District assembly awarded the construction of a Police Station at Akontombra worth GHS256,541.01, out of which GHS237,051.37 had been paid to the contractor.

The project was scheduled to be completed on June 10, 2016, but had been abandoned for 49 months due to a purported lack of funds.

There were also instances where local assemblies had completed projects that were not put to use “as a result of non-availability of water and electricity connection, defects and lack of furnishing or siting of projects beyond easy access of the communities.”

This cost Ghana GHS8.6 million.

In the Wassa Amenfi East Municipal, for instance, GHS214,352 was spent to construct a Police Post at Nkonya in 2017, but the facility is currently not in use.

“We further noted that payments were made for unexecuted contracts, unjustified contingencies and shoddy works,” the report also noted.

As part of the recommendation, the Auditor-General’s department advised the local assemblies to prioritise ongoing projects for completion before the commencement of new ones.

It also recommended that defects on the completed projects should be fixed and provide the ancillary facilities needed, so such facilities could be put to use for the avoidance of additional costs resulting from deterioration.

“We further recommended recovery for payments for unexecuted contracts, unjustified contingencies from the Chief Executives, Coordinating Directors, Finance Officers and Works Engineers,” the report added.

Overall, deficiencies noted in the operations of the Assemblies created avenues for some officials to mismanage funds and resources of the Assemblies to a financial value of approximately GHS77.14 million.

Aside from contract, procurement, the deficiencies were identified in transactions under account areas such as cash management and tax irregularities.

Like in previous reports, the Auditor-General’s department also recommended punitive actions against the management and staff of local assemblies who mismanaged the resources brought under their care.

Tags: Abandoned projectAuditor-GeneralDistrict Assemblies Common Fund
ShareTweetSendSend
Previous Post

28 OMCs failed to pay taxes worth GHS226.9M between 2018 and 2019 – Audit Report

Next Post

‘Fixing Ghana is a collective responsibility’ – Chief of Chiraa to Ghanaians

Related Posts

Director-General of the Ghana Broadcasting Corporation (GBC), Prof. Amin Alhassan
Featured

All-African Games: GBC defends broadcast decisions cited in audit report

June 1, 2026
Featured

Publish arrears yearly or risk fiscal leakage — PAC tells govt

May 21, 2026
Featured

DACF: Nearly GH¢8bn worth of projects unfinished across Ghana

May 6, 2026
President of Ghana, John Dramani Mahama
Featured

New High Courts to handle Auditor-General cases – Mahama

May 1, 2026
Auditor-General Johnson Akuamoah Asiedu
Featured

GH₵427m salary claim was transpositional error — Auditor-General apologises

April 21, 2026
Featured

MMDAs received GH¢5bn in 2025, up from only GH¢362m in 2024 — Ahmed Ibrahim

April 20, 2026
Next Post

'Fixing Ghana is a collective responsibility' - Chief of Chiraa to Ghanaians

ADVERTISEMENT
Citinewsroom - Comprehensive News in Ghana

CitiNewsroom.com is Ghana's leading news website that delivers high quality innovative, alternative news that challenges the status quo.

Archives

Download App

Download

Download

  • About Us
  • Privacy Policy
  • Terms of Use
  • Breaking News
  • Explainers
  • Listen Live

© 2024 All Rights Reserved Citi Newsroom.

No Result
View All Result
  • Home
  • News
    • Regional News
      • Ahafo Region
      • Ashanti Region
      • Bono East Region
      • Bono Region
      • Central Region
      • Eastern Region
      • Greater Accra Region
      • Northern Region
      • North East Region
      • Oti Region
      • Savanna Region
      • Upper East Region
      • Upper West Region
      • Volta Region
      • Western Region
      • Western North Region
  • Sports
    • World Cup
  • Politics
  • Business
  • Entertainment
  • Articles
  • Explainers
  • Editorials

© 2024 All Rights Reserved Citi Newsroom.